Project Website: http://www.chiangmai-transitredline.com/
Detail | Cost (Unit: Million baht) |
Land Acquisition | 2,2861.88 |
Civil works | 21,040.21 |
M&E Works and Rolling Stocks | 3,683.6 |
Consultant Fee | 826.47 |
Provisional Sum | 1,111.14 |
Total | 29,523.29 |
Chiang Mai Transit Red Line Consultants Consortium (CMTR), February 2022