Project Cost

17 October 2565
Detail
Cost (Unit: Million baht)
Land Acquisition
2,2861.88
Civil works
21,040.21
M&E Works and Rolling Stocks
3,683.6
Consultant Fee
826.47
Provisional Sum
1,111.14
Total
29,523.29