Project Cost

17 October 2565
Detail
Cost (Million baht)
Land Acquisition
15,913.00
Property Survey
28.73
Civil Works
77,385.00
Civil Works (Compensation for Agencies affected by Project Construction)
1,335.00
Consultant Fee for Management and Construction Control
2,865.00
Provisional Sum of Civil Works
3,582.00
M&E Works and Rolling Stocks
23,064.00
Consultant Fee for M&E Works
615.00
Total
124,787.73