17 October 2565| Detail | Cost (Million Baht) |
| 1) Land Acquisition | 7,254 |
| 2) Civil Work | 20,864 |
| 3) M&E Work | 19,013 |
| 4) Project Consultant | 1,255 |
| Total | 48,386 |
| Detail | Cost (Million Baht) |
| 1) Land Acquisition | 7,254 |
| 2) Civil Work | 20,864 |
| 3) M&E Work | 19,013 |
| 4) Project Consultant | 1,255 |