Project Cost
17 October 2565| Detail | Cost | Unit |
| Land Acquisition | 7,878 | million baht |
| Consultant Fee for Management and Construction control | 1,062 | million baht |
| Civil Works | 26,569 | million baht |
| Provisional Sum of Civil Works | 2,656 | million baht |
| M&E Works | 20,056 | million baht |
| Consultant Fee for M&E Works | 641 | million baht |
| Total | 58,862 | million baht |
Source
Budget follows the draft bill authorises the Finance Ministry to borrow money for the country’s transportation infrastructure.