BACKGROUND

     The Cabinet meeting on December 4th, 2018 acknowledged the Commission for the Management of Land Traffic's resolution in the 2/2018 meeting on October 17th, 2018, to include the MRT Pink Line Extension (Spur Line) Project; Si Rat - Muang Thong Thani section, in the Mass Rapid Transit Master Plan (M-MAP).


CHARACTERISTICS

     The MRT Pink Line Extension was designed as a minor mass transit system (Feeder) in terms of the elevated straddle monorail.


 Alignment

     Connected to the MRT Pink Line at the Muang Thong Thani Station (PK10) and run along the Chaeng Wattana - Pak Kret 39 road to end at the lake in the Muang Thong Thani zone; the length of this alignment is approximately 3 kilometers.


Station

     There are two stations; the 1st station is the Impack Muang Thong Thani (MT01), and the 2nd station is the Lake Muang Thong Thani (MT02).


Depot

     The MRT Pink Line Extension shares the same depot with the MRT Pink Line Project, Khae Rai - Min Buri.


PROJECT COST 4,100 Million Baht (Approximately)


Source: The project consultant for the MRT Pink Line Extension (Spur Line) project, Si Rat - Muang Thong Thani section: Monthly Progress Report at July 2022.